Notification of upcoming road closure Coventry Road, Cubbington.
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Prog-works-20-06/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Cubbington
- Worksite Name
- Coventry Road
- Contractor
- BBV JV
- Type of works
- Construction, Road closure
- Estimated Start Date
- 15/11/2021
- Estimated End Date
- 01/12/2021
What we are doing
We will be creating a controlled crossing on Coventry Road, Cubbington.
This crossing will allow us to safely move our construction plant across the road as we undertake various earthworks in the area.
On completion of the plant crossings, the lights will be set to green and will only turn to red when site vehicles require to cross the road. To further reduce disruption, these lights will be manned during busier periods of the day. This will help to aid the flow of traffic and reduce disruption. Please note that these works are subject to weather conditions.
We will be carrying out these works in two stages. Stage one will be from 18 October to 28 October 2021. We will reopen the road after the 28 October and then close it again from 15 November to 1 December 2021 to carry out stage two of the works.
The road will be closed 24-hours, seven days a week including weekends. Please note that access will be maintained to all properties and businesses on Coventry Road while the works take place.
The plant crossing will become operational from 6 December 2021 and will operate during permitted working hours.