Notification of works on M42/M6 link road westbound near Water Orton

Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-19-06/01/2021

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Water Orton
Contractor
BBV JV
Type of works
Traffic management, Vegetation clearance
Estimated Start Date
05/06/2021
Estimated End Date
13/06/2021

What we are doing

Subject to consents being accepted we will be undertaking vegetation clearance and ground investigation survey works on the M42/M6 link road westbound.

The works are planned to take place overnight from Saturday 5 June until Sunday 13 June. In order to undertake our works safely, BBV will work with Highways England to implement temporary closures of the M42/M6 westbound link road from 9pm – 5am throughout the duration of works.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]