Notification of works to the east of A446 Lichfield Road, Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-18-01/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Worksite / compound set-up
- Estimated Start Date
- 28/03/2022
- Estimated End Date
- 31/08/2022
What we are doing
The work we will be doing
BBV will look to begin works to the east of the A446, to the north of Gorsey Lane. The works set to be complete will be to create a site access into land to the east of the A446, which will be used as our construction access for works in that area.
In order to complete these works, we will need to access and exit site via Gorsey Lane from the A446 and turn left into our working area. We have a maximum of 12 HGV movements in and out of our working area.
We will only access Gorsey Lane via the A446 and we will have a road sweeper who will manage the cleanliness of the roads.
Our working hours will be 8am – 6pm Monday to Friday and 8am – 1pm on Saturdays.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]