View route map
Off-peak survey and monitoring works on M25, Denham to Maple Cross, junctions 16 and 17
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-1-14/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hertfordshire
- Location
- Denham
- Worksite Name
- M25
- Contractor
- Align JV
- Type of works
- Maintenance work
- Estimated Start Date
- 18/01/2022
- Estimated End Date
- 18/05/2022
What we are doing
HS2 contractors Align JV will be carrying out monitoring and maintenance works on the M25, on both the clockwise and anti clockwise emergency lane/hard shoulder between Junction 16 (Denham Interchange) and Junction 17 (Maple Cross Interchange). The maintenance work will be carried out across four days on two separate occasions during the daytime, Tuesday 18 to Wednesday 19 January 2022 and Tuesday 17 to Wednesday 18 May 2022.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]