Old Oak Common Lane closure – Network Rail and HS2 Ltd
Work item: HS2-MW-BBVS-Ph1-Ar-Ce-C2-Traf-16-22/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- Network Rail
- Type of works
- Road closure
- Estimated Start Date
- 28/06/2021
- Estimated End Date
- 11/07/2021
What we are doing
Our Ref: Old Oak Common Lane closure – Network Rail and HS2 Ltd
Dear neighbour,
We are temporarily closing Old Oak Common Lane between Wells House Road and Wulfstan Street to cars and lorries between 01:00 on 28 June until 23:00 on 11 July. 28 June and 11 July. This means there is a diversion in place via Wales Farm Road (map overleaf) and access to Wells House Road is maintained.
There will be 24/7 access for pedestrians. Cyclists will be asked to walk their bikes through. There is pre-arranged, managed access for the immediately affected businesses. If you believe this is you and you haven’t made arrangements please contact [email protected].
Minimising ongoing disruption
As you will be aware, Old Oak Common is the location for HS2’s new station, which is being constructed and enabled by lots of different organisations. To reduce ongoing disruption Network Rail has collaborated with these organisations so that everyone uses the same road closure. This will help reduce ongoing disruption to residents and businesses throughout the summer. Our approach has been approved by Ealing Council.
What work are we doing?
Who? | What? | When? |
HS2 enabling work by Network Rail | ||
Cadent Gas | Breaking out the road and removing gas connection to the old HEX depot | 28 June – 02 July 08:00 to 18:00 Monday to Friday |
Southern and Scottish Electricity Network | Removing the electricity connection to the old HEX depot | 05 July – 09 July 08:00 to 18:00 Monday to Friday |
Thames Water | Breaking out the road and removing the water connection to the old HEX depot and fixing the water leak | 10 July – 11 July 08:00 to 18:00 Monday to Friday |
Maintenance by Network Rail’s Western Route | ||
Balfour Beatty | Putting up pigeon netting and improving drainage underneath the railway on Old Oak Common Lane | 28 June – 10 July 8am to 6pm Monday to Friday |
HS2 Ltd | ||
BBVS Joint Venture | Vegetation Clearance on Wells House Road Boundary Wall. We will be removing the vegetation from the boundary wall | 28 June – 10 July 08:00 to 18:00 Monday to Friday; and 8am to 1pm on Saturdays
|
BBVS Joint Venture
| Vegetation Clearance on Old Oak Common Station Site. Operatives will be removing the vegetation and the tree stumps on opposite Wells House Road within the Old Oak Common Station Site | 5 July- 7 July 08:00 to 18:00 Monday to Friday; and 08:00 to 13:00 on Saturdays |
BBVS Joint Venture
| Ground Investigation works to the abutments underneath the bridge on Old Oak Common Lane | 28 June – 10 July 08:00 to 18:00 Monday to Friday; and 08:00 to 13:00 on Saturdays |
BBVS Joint Venture
| Re-creating the access road on the Wycombe Single Line Bridge. This work will involve installing more ballast (material used for the track bed) to make the deck flat for a vehicle to cross | 5 July- 10 July 08:00 to 18:00 Monday to Friday; and 08:00 to 13:00 on Saturdays |
BBVS Joint Venture
| Re-creating the access road on the Wycombe Single Line Bridge. This work will involve installing additional ballast to make the deck flat | 28 June- 10 July 08:00 to 18:00 Monday to Friday; and 08:00 to 13:00 on Saturdays |
BBVS Joint Venture
| Vegetation Clearance to the north-west corner of the site on Old Oak Common Lane | 28 June- 10 July 08:00 to 18:00 Monday to Friday; and 08:00 to 13:00 on Saturdays |
Any questions?
- You can contact Network Rail on:
Please do not hesitate to contact us if you have any additional questions or concerns. You can call us 24 hour a day on 03457 11 41 41.
- You can contact HS2 Ltd on:
If you have any questions about HS2, please contact the HS2 helpdesk which is available 24 hours a day on 08081 434 434 or email [email protected]
If you have any outstanding questions, the Network Rail team and HS2 Ltd will be holding a Q&A session on Wednesday 23 June at 18:30 – 19:30.
You can join via a Teams – there are three ways:
- Click here to join the meeting
- Type this into your browser: https://bit.ly/3zD99o8
- Or call in +44 20 3321 5223,,697443739# Phone Conference ID: 697 443 739#
Yours sincerely,
Emily Hanlon
Community Relations Executive
Network Rail (HS2 ONW)
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]