Old Oak Common Station conveyor removal 12 – 24 July

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-37-09/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Worksite Name
Old Oak Common
Contractor
BBVS JV
Estimated Start Date
12/07/2024
Estimated End Date
21/07/2024

What we are doing

Removal of conveyor 12 – 21 July 2024

We are removing the conveyor which has been used for transporting excavated material from the Old Oak Common Station site to the Willesden Euroterminal site. The excavation works is now complete. Removing the conveyor will also enable the installation (at a future date) of a temporary UK Power Networks (UKPN) power cable bridge over Old Oak Common Lane until the permanent cabling is installed. This is part of the future utility works on Old Oak Common Lane. We will be excavating two trial holes during the road closure.

The impact on the community – road closures

The conveyor removal will affect local residents due to road and footpath closures, noise, and some floodlighting (which will be directed away from local properties). Further details are on the following pages.
The works are summarised below:
1. Conveyor bridge removal pre-works. Road closure: 10pm Friday 12 July 2024 to 5am Monday 15 July 2024.
2. Removal of conveyor bridge crossing Old Oak Common Lane and large crane from site. Road closure: 10pm Friday 19 July 2024 to 10pm Sunday 21 July 2024. The road closure prevents traffic passing directly underneath the conveyor as we are removing it.
The footpath will be closed and there will be no pedestrian access on Saturday 13 July 12.00am – 09.00am and Friday 19 July 11.00pm – Saturday 20 July 5.00pm. These times are subject to change depending on the progress of works.

 

Vehicle diversion routes

During the closures, a diversion route will be in place as follows:
Diversion route: Old Oak Lane – Station Road – High Street Harlesden – Scrubs Lane – Du Cane Road – Old Oak Common Lane
We would like to apologise for the disruption that these works will cause, and we are trying to minimise the impacts of these works as much as possible. Please see map attach below with further information.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]