Old Oak Common Tunnel

Work item: HS2-EW-SCS-Ph1-Ar-So-S1 - Tun-1-30/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Old Oak Common lane, Wells House Road
Worksite Name
Old Oak Common
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
22/04/2024
Estimated End Date
27/09/2024

What we are doing

In April 2024 we  started work on the Old Oak Common (OOC) tunnel connecting the Victoria Road Crossover Box to the to the Old Oak Common station site on Old Oak Common Lane. We’ll finish building this tunnel in late 2025,  and works will be 24 hours a day, 7 days a week when required.

The 360-metre long OOC tunnels will be 12 metres below ground (to the crown of the tunnel). The tunnel will be built using a sprayed concrete lining (SCL) method, involving rapidly spraying the excavated ground with concrete to stabilise it to form the permanent tunnel lining.

Unlike bored tunnels, which are built using a tunnel boring machine, the SCL method allows variation in the tunnel shape and diameter of the tunnels, which are required in this location. The width of the tunnels varies as they approach Old Oak Common Station to allow for track separation as trains are changing tracks when travelling to and from the station.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]