Ongoing temporary closure of Robert Street

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Traf-12-21/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
20/08/2024
Estimated End Date
02/09/2024

What we are doing

We recently wrote to you (reference: HS2-MW-MD-Ph1-Ar-So-S1-Traf-37-25/07/2024) regarding works on Hampstead Road. These works require temporary closure of Robert Street. This is to ensure the safety of cyclists and how they interface with vehicles on Hampstead Road.

We recognise that Robert Street was reopened in error. To keep cyclists safe, we need to keep a section of road closed to vehicles. This closure will continue until UKPN complete their works on Hampstead Road. We expect Robert Street to reopen early September 2024.

We recognise that construction work can be disruptive to those living and working nearby. We always try to complete works as quickly as possible, but please be aware the timeframe given above is a guide and that technical difficulties may mean the timings can change. We are working to reopen the road as soon as possible. Thank you for your continued patience during these much needed works.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]