Ongoing works at North Embankment, Denham

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-09-19/03/2025

Work Item Summary

Project Phase
Phase 1
Location
Colne Valley
Worksite Name
North embankment
Contractor
Align JV
Type of works
Construction
Estimated Start Date
01/03/2025
Estimated End Date
31/08/2025

What we are doing

We have now completed the installation of both parapets (walls of the viaduct) and noise barriers on the Colne Valley viaduct as it crosses the A412.

Work began last October 2024 to prepare the foundations for the construction of the concrete noise barriers which begin where the Colne Valley viaduct starts and then stretch back northwards for nearly 500 metres either side of the railway line. The concrete noise barriers will be 4m tall and are part of the screening for the operational railway. These works will start in April 2025 until June 2025.  We will do all we can to minimise noise.

Download information relating to these works