Out of hour deliveries to Atlas Road site

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-7/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Atlas Road
Worksite Name
Old Oak Common
Contractor
SCS JV
Type of works
Delivery of materials
Estimated Start Date
11/07/2022
Estimated End Date
19/07/2022

What we are doing

Out of hour deliveries to the Atlas Road site
We wrote to you in June 2022 regarding ongoing works at the Atlas Road site and the extended working hours for various activities.

Further details of these works can be viewed at https://www.hs2.org.uk/in-your-area/map/

As part of these ongoing works, we would like to inform you of a series of out of hour deliveries occurring on site on the dates below.
• Monday 11 July from 9pm
• Tuesday 12 July from 9pm
• Monday 18 July from 9pm
• Tuesday 19 July from 9pm

The equipment being moved is classified as a wide load and has to be moved outside of road peak times for safety reasons and reduced impact to the road network.
There will be a total of three deliveries during the night lasting approximately one hour each.

Deliveries will enter and exit our site via the gate on Atlas Road. You may notice some additional noise and light from site during the offloading operations and the arrival and departure of the low loader truck.
We will continue to monitor our works to ensure that any disruption is kept to a minimum.

Dates and times mentioned in this notification may change – we will provide updates at https://www.hs2.org.uk/in-your-area/map/

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]