Out of hours crane removal at Mandeville Road site

Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Prog-works-9-18/02/2022

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Crane removal
Estimated Start Date
28/02/2022
Estimated End Date
04/03/2022

What we are doing

Crane removal
From 28 February to 4 March 2022, a crane and sheet piling equipment will be removed from site. Works to prepare the crane and equipment will be completed during core hours, 8am to 6pm. The vehicles, however will need to leave site outside of these times. The lorries will leave site between 7pm and 9pm due to road restrictions in London.

Traffic management will be in place for safety reasons because the lorries will need to leave the site and head northbound towards Northolt Park due to restrictions within the site entrance.

How these works might affect you
You may notice periods of increased vehicle movement during this time and flashing lights may be seen during the crane removal.

Temporary traffic management will be in place on north and southbound carriageways of Mandeville Road.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.