View route map
Out of hours deliveries to Old Oak Common station
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Traf-1-23/05/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Old Oak Common
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Large load delivery/collections, Tunnel segment delivery
- Estimated Start Date
- 07/06/2024
- Estimated End Date
- 05/10/2024
What we are doing
Between Friday 7 June and Saturday 5 October 2024, we have a schedule of planned deliveries of TBM segments to the Old Oak Station site on Old Oak Common Lane.
These deliveries will consist of large loads and are expected to arrive on site at around 10pm, outside our core working hours. This is to ensure that there is reduced traffic flow on designated routes to help minimise any disruption to the road network.