Skip to main page content
View route map

Out of hours deliveries to Old Oak Common station

Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Traf-1-23/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Old Oak Common
Worksite Name
Old Oak Common
Contractor
SCS JV
Type of works
Large load delivery/collections, Tunnel segment delivery
Estimated Start Date
07/06/2024
Estimated End Date
05/10/2024

What we are doing

Between Friday 7 June and Saturday 5 October 2024, we have a schedule of planned deliveries of TBM segments to the Old Oak Station site on Old Oak Common Lane.

These deliveries will consist of large loads and are expected to arrive on site at around 10pm, outside our core working hours. This is to ensure that there is reduced traffic flow on designated routes to help minimise any disruption to the road network.

 

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]