Out of hours delivery to Adelaide Road Site

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Traf-1-20/09/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Adelaide Road
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Large load delivery/collections
Estimated Start Date
27/09/2023
Estimated End Date
27/09/2023

What we are doing

Early morning delivery to site
On Wednesday 27 September we are expecting a delivery of machinery to the Adelaide Road Ventilation Shaft and Headhouse site.
The delivery is scheduled to arrive before 8am, outside our core working hours. This is to ensure safe delivery of abnormal loads during reduced traffic flow on designated routes.

How will this affect you?
You may hear reversing signals and engine noise during the delivery.
We will be monitoring the noise levels to ensure minimal disruption to residents.
We apologise for any inconvenience this delivery may cause.