Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-22-03/01/2023

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
Solihull
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
25/03/2023
Estimated End Date
03/04/2023

What we are doing

Overnight closure of A452 northbound slip road

BBV have been significantly reconfiguring the Junction of the A446 Stonebridge Road and A452 Chester Road near Birmingham Business Park. The new bridge over the M42 is already taking some vehicular traffic using a temporary lane configuration. As we prepare for its permanent and intended configuration some remedial work is required such as removal of temporary safety barriers, surfacing works and additional electrical and drainage work. To minimise any disruption the work will only take place at night on weekdays but will involve a full closure over the weekend.

From 9pm until 5am between 27 March and 31 March then all day and all night from 9pm on 31 March until 5am on 3 April.