Overnight closure of Moorhall Road, Hillingdon, for parapet installation

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-06-12/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire, Hertfordshire, Hillingdon
Location
Moorhall Road
Contractor
Align JV
Type of works
Road closure
Estimated Start Date
12/08/2024
Estimated End Date
25/08/2024

What we are doing

Align JV is currently building the 3.4km Colne Valley viaduct from the North Embankment at Denham in Buckinghamshire to the South Embankment near Harvil Road in Hillingdon. The decking of the viaduct over Moorhall Road has already been completed however we now need to install parapets – walls either side of the deck. We have already installed some parapets along the viaduct, but to install the sections safely over the public highway we will need to close Moorhall Road to all users overnight from Monday 12 August 2024 to Sunday 25 August 2024 between 10pm and 6am every night.

Traffic will be diverted during these times.