Overnight grouting work at South Ruislip ventilation shaft site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-09/06/22

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
South Ruislip
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Borehole works, Grouting
Estimated Start Date
23/06/2022
Estimated End Date
14/10/2022

What we are doing

What we are doing
In advance of tunnelling later this year, we need to drill boreholes and infill grouting to prepare the ground for tunnelling. This will take place from 23 June to 14 October 2022, Monday to Friday 24 hours a day.

We will use three drilling rigs, a dumper for moving muck away from the bore hole and an excavator.

Noise reduction fencing will be used at night, where possible, to reduce the noise levels.

How the work might affect you
The team will use electric powered lighting and machinery to reduce noise impacts on the local community.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.