What we are doing
Temporary overnight lane closures along short sections of the A452 northbound and southbound near Stonebridge Island in September 2021
As part of our preparation works for future construction of the HS2 Interchange Station and railway route, we are undertaking environmental surveys in the Interchange area. To safely carry out our works, we will install traffic measures when necessary.
Subject to obtaining the relevant consents, we will install temporary, phased overnight lane closures along short sections of the A452 northbound and southbound near Stonebridge Island from 7pm to 7.30am on Thursday 9 September, Monday 13 September and Monday 20 September.
These traffic measures will be carried out in conjunction with a new direction of travel for road users around Northway Island, which commenced on Monday 23 August.