Overnight Lawley Middleway lane and footpath closures
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-34-13/03/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Birmingham
- Contractor
- BBV JV
- Type of works
- Footpath closures, Lane closure
- Estimated Start Date
- 27/05/2024
- Estimated End Date
- 16/06/2024
What we are doing
In preparation for our plan to push a bridge over Lawley Middleway to carry the HS2 railway over the dual carriageway, we need to implement a series of single lane and footpath closures.
From Monday 27 May to Sunday 16 June 2024, will first close a single lane and the footpath on Lawley Middleway northbound. Once these works are complete, we will reopen the lane and footpath and then close a single lane and the footpath on Lawley Middleway southbound.
During this time, we will keep a single lane open for traffic and direct pedestrians to the footpath on the other side of Lawley Middleway. Lawley Middleway northbound will remain fully open.
Download information relating to these works