Updated notice of overnight road closure Diddington Lane, Hampton-in-Arden

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-30-23/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
Hampton in Arden
Contractor
BBV JV
Type of works
Overnight road closure, Utility works / surveys
Estimated Start Date
03/07/2023
Estimated End Date
28/07/2023

What we are doing

*Updated notice*

UPDATE

We previously contacted you to inform you that this work would commence on 19 June. Due to an incident this work has been delayed and we now intend to start this work on 3 July.

The road will be closed between 8pm and 6am Monday – Friday from 3 July until 28 July 2023.

The new railway will pass over the River Blythe on a viaduct before entering a deep cutting on the approach to the A45. Before we start to excavate the cutting there are a number of utilities that will need to be safely diverted to avoid interrupting the supply. To minimise disruption, we will close Diddington Lane at night only, between 8pm and 6am on weekdays. Access for residents will be maintained at all times. You can expect only a very low level of noise which will be monitored at all times.

The road will be closed between 8pm and 6am Monday – Friday from 11 April until 6 May 2023.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]