Skip to main page content
View route map

Overnight road closure on Breakspear Road South

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-03/01/2023_03

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
Breakspear Road South
Worksite Name
West Ruislip
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
15/03/2023
Estimated End Date
20/03/2023

What we are doing

Works along Breakspear Road South, north and south of the Network Rail bridge will take place overnight from 15 to 20 March 2023.

The works will include the following activities:
• concrete pour for the deck of the new bridge over Breakspear Road South;
• utility investigation works between the HS2 bridge and the Network Rail bridge;
• installation of the conveyor bridge (for the removal of tunnel excavation arisings from West Ruislip Portal to the Southern Sustainable Placement Area). These works are dependent on weather conditions and we will therefore need to work 25 and 26 March to complete the installation; and
• installation of road line markings and highways signage onto the masonry of the Network Rail bridge.
During the road closure access will be maintained for residents and emergency services.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]