Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-16/11/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
27/11/2023
Estimated End Date
03/12/2023

What we are doing

From 27 November to 3 December 2023 we will be installing a new sewer lining to strengthen and protect the existing sewage structure once tunnelling begins.

These works will take place from 8pm to 8am Monday to Sunday. You may notice increased noise from our compressor machine for short periods of time and movement of trucks.

We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]