Overnight Transportation of Piling Rig
Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-27-09/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Camden
- Contractor
- Mace Dragados JV
- Type of works
- Enabling works
- Estimated Start Date
- 14/09/2021
- Estimated End Date
- 14/09/2021
What we are doing
On Tuesday 14 September 2021 we need to temporarily close Drummond Street (pedestrian corridor) for 1 hour between 1:30am until 7am. This is to facilitate the delivery of a piling rig, crane and excavator from St James Garden site to the Wolfson site. At the same time, we will remove some of the hoarding panels to create room for the materials to be transported through the area. Because of the live railway these activities can only be carried out when the trains are not running.
To help people navigate through the area, we will be placing marshals on either side of the closure to help direct people and answer their questions.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]