Overnight utilities work on Oldfield Lane North, Greenford

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-27/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Greenford, London
Location
Oldfield Lane North
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
11/04/2023
Estimated End Date
10/05/2023

What we are doing

From 11 April to 10 May 2023, we will be carrying out the main sewer protection works on Oldfield Lane North. This work will be carried out overnight between 7pm and 7am. The main sewer protection works consist of relining the foul and surface sewer network and replacing maintenance covers. Work will take place in four phases:

Phase 1
11 and 12 April – Compound set up on Uneeda Drive during core hours 8am to 6pm.

13 to 17 April – Install pipe lining, opposite Greenford Station 7pm to 7am. Road closed from Station, under bridge to Rockware Avenue.

Phase 2
20 to 24 April – Install pipe lining under bridge between Greenford Station and Rockware Avenue 7pm to 7am

Phase 3
27 to 30 April – Install pipe lining from Bridge past Rockware Avenue 7pm to 7am

Phase 4
4 to 7 May April – Install pipe lining from Bridge past Rockware Avenue 7pm to 7am

9 and 10 May – Demobilisation of compound on Uneeda Drive during
core hours 8am to 6pm.