Overnight utility drainage survey on Hilgrove Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-27/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 19/11/2021
- Estimated End Date
- 20/11/2021
What we are doing
Utility drainage surveys on Hilgrove Road
We will be carrying out drainage surveys on Hilgrove Road between the junction with Belsize Road / Loudoun Road and Adelaide Road overnight on 19 November.
These surveys will help us understand the condition of the drainage system in the area and how to best protect them during the construction of the railway. We will investigate the condition of the sewer system using a camera and may need to flush the drainage using a high-pressure water jet if any blockages are found. You may notice additional noise during this activity.
The surveys will take place between 9pm and 6am the following morning. In order to carry out these works safely, we will set up a safety exclusion zone around our working area. Signage will be in place to advise motorists and pedestrians of our work. We will also maintain traffic flow with the aid of stop and go boards being used by staff on site.
A map showing the location of these works can be found on the following page.
We estimate the surveys to last approximately 30 minutes. Your utility services will not be affected during these works.
Dates mentioned in this notification may change due to unforeseen circumstances – we will keep you informed of any changes and will provide updates at Hs2.org.uk.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]