Overnight weekend works at Granby Terrace bridge in October

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-27/09/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Granby Terrace bridge
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Bridge works
Estimated Start Date
05/10/2024
Estimated End Date
06/10/2024

What we are doing

Overnight works at Granby Terrace bridge
We are currently working to extend Granby Terrace bridge. We previously informed you we would need to work occasionally at weekends and at night to complete this work.

  •  We will work overnight, from 9pm Saturday to 12pm Sunday, every weekend from 12 to 27 October.
  •  We will work extended hours, from 8am to 5pm, on two non-consecutive Saturdays each month. The dates for these will change each month but we will not work two weekends in a row. Please see the link to the previous notification.

For safety, we can only carry out this work when the tracks below are not in use. We will limit all noisy works to before 1pm and monitor noise levels closely to ensure we are working within the approved limits.

Overnight works at track level in Camden Cutting – 5 to 6 October 2024
We need to install new fences between our work site in Camden Cutting and the Network Rail tracks overnight on Saturday 5 October to Sunday 6 October. This will take place between midnight and 5am.

For safety, we can only install these fences when the tracks below are not in use. We do not expect these works to be noisy. Again, we will monitor noise levels closely to ensure we are working within the approved limits.

We apologise for any disruption these works may cause.

For further details please follow the link to the notification below.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]