Park Village East works; one-way traffic ongoing until August

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-15/06/2023

Work Item Summary

Project Phase
Phase 1
Location
Park Village East
Contractor
SCS JV
Type of works
Hoarding works, Utility works / surveys
Estimated Start Date
05/06/2023
Estimated End Date
05/08/2023

What we are doing

Southbound traffic only on Park Village East between Parkway and Augustus Street – until August

We are currently replacing the hoarding at the southern end of Park Village East. We recently informed you that vehicles will only be able to travel south on Park Village East until the end of June. Due to delays, this traffic management will remain in place until early August. Cyclists will still be able to travel in both directions. A section of the lane and footpath next to the hoarding will also remain closed.

Lane narrowing and parking bay suspensions on Park Village East north – 3 to 5 July

We recently informed you we will suspend parking bays and narrow the lane in front of 16 and 22 to 24 Park Village East, for utility works. These works have been postponed until 3 July.

We will work from 8am to 8pm to complete the work as soon as possible and re-open the parking bays.

We will also close a small section of the footpath and suspend five parking bays on corner of Park Village East and Augustus Street, for a utility survey. This survey was planned for 25 June but has now been rescheduled for 5 July.

For details of the previous notification of above works please follow the link to ‘Works on Park Village East – 5 to 30 June’ (May 2023).

For further updates of above works please see notification below.