Update: Piling and drainage installation works for noise barrier sites

Work item: HS2-SCS-25-1073

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Worksite Name
West Ruislip
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
28/07/2025
Estimated End Date
27/03/2026

What we are doing

We planned to carry out the installation of noise barriers and drainage systems along the HS2 route from Copthall Tunnel to West Ruislip Portal sites, from 30 June 2025 to 27 March 2026.

However, these works have been rescheduled, and we will now be starting from 28 July 2025.

We will start by installing concrete piles to stabilise the ground, followed by the installation of drainage systems. Our working hours will be Monday to Friday 8am to 6pm and Saturday 8am to 1pm.

You may notice periods of increased noise during these works. However, noise monitoring will take place throughout the works.