Piling in Camden Cutting north

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-26/05/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden Cutting north
Worksite Name
Camden Cutting north
Contractor
SCS JV
Type of works
Piling
Estimated Start Date
01/06/2023
Estimated End Date
20/08/2023

What we are doing

We are currently installing piles at the northern end of our worksite, in the narrow space between the tracks and the retaining wall.

In June we will move onto the section closest to Parkway and continue piling until September 2023.

We will continue to receive deliveries to our worksite via the lorry lay-by on Park Village East north. You may notice periods of increased noise from the piling rig and excavator. We will monitor our works closely to ensure we are operating within approved noise and vibration limits.

Our working hours are Monday to Friday 8am to 6pm and Saturday 8am to 1pm. However, we need to complete the concrete pour for each pile within a single shift. This means we will sometimes work until as late as 10pm to finish a pile.

For further details and location map please see notification below.

 

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]