Piling in Camden Cutting north
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-26/05/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden Cutting north
- Worksite Name
- Camden Cutting north
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 01/06/2023
- Estimated End Date
- 20/08/2023
What we are doing
We are currently installing piles at the northern end of our worksite, in the narrow space between the tracks and the retaining wall.
In June we will move onto the section closest to Parkway and continue piling until September 2023.
We will continue to receive deliveries to our worksite via the lorry lay-by on Park Village East north. You may notice periods of increased noise from the piling rig and excavator. We will monitor our works closely to ensure we are operating within approved noise and vibration limits.
Our working hours are Monday to Friday 8am to 6pm and Saturday 8am to 1pm. However, we need to complete the concrete pour for each pile within a single shift. This means we will sometimes work until as late as 10pm to finish a pile.
For further details and location map please see notification below.