Plant crossings at A412 North Orbital Road and Moorhall Road

Work item: HS2-MW-Align-Ph1-Ar-Ce-C2-Traf-1-02/02/2022

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Moorhall Road
Worksite Name
Moorhall Road
Contractor
Align JV
Type of works
Traffic management
Estimated Start Date
16/02/2022
Estimated End Date
31/07/2022

What we are doing

To enable the crossing of heavy or abnormal loads between the HS2 compounds on either side of A412 North Orbital Road, near Denham Water Ski Club, and between Moorhall Road North and South compounds in Hillingdon, short road closures will be required on occasion during the evenings from February 2022 to late July 2022. We will safely hold traffic at signals whilst heavy plant or abnormally long vehicles cross.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]