Update on new dates for platform and steel beam installation, Mandeville Road Vent Shaft site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-2-15/08/2024_2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Platform and steel beam installation
- Estimated Start Date
- 21/10/2024
- Estimated End Date
- 29/11/2024
What we are doing
From 21 October to 15 November 2024, we planned to building a platform that will be used to install twelve steel beams into the ground to the eastern end of the Mandeville Road Vent Shaft site. This is in preparation for construction of the Headhouse.
Due to other ongoing works on-site and late delivery of some materials, we now expect these works will continue until 29 November 2024. All works will be during our core working hours of Monday to Friday 8am to 6pm.
To avoid banging the steel beams into the ground using hammer or vibration methods, we will drill holes into the ground and install the beams into these holes. You may notice noise from the construction machinery. We would like to apologise for any disruption or inconvenience this may cause.
Download information relating to these works