Update on new dates for platform decking works, Mandeville Road Vent Shaft site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-09/08/2024_2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Decking Platform works
- Estimated Start Date
- 28/10/2024
- Estimated End Date
- 01/11/2024
What we are doing
What we are doing
From 21 to 25 October 2024 we planned to installing a platform between the sheet piles at the northern end of the site. The platform will be used for storage of materials that we need to relocate in preparation for future works.
Due to delays in finalising design for these works they are now to be carried out from 28 October to 1 November 2024. All works will be during our core working hours of Monday to Friday 8am to 6pm. We will keep you updated if dates change.
During these dates we will be using cutting and grinding tools to erect the steelwork. You may notice more noise from the tools we’ll be using. We will use noise reducing barriers to help keep noise and vibration to a minimum.
We would like to apologise for any disruption or inconvenience this may cause.