Power cable duct installation work in west of Euston station

Work item: UK Power Networks - Modus works

Work Item Summary

Project Phase
Phase 1
Location
Cobourg Street, Euston Road, Hampstead Road, North Gower
Contractor
UK Power Networks
Type of works
Utility works / surveys
Estimated Start Date
26/09/2022
Estimated End Date
09/12/2022

What we are doing

UK Power Networks are in process of installing a new connection to the electricity network in the Camden area.

The works are progressing through the next sections and will affect areas in Drummond Street, Euston Street, North Gower Street, Cobourg Street and Starcross Street.

Works are due to commence on Monday 26th September and be completed early December 2022.

Working hours:  Monday to Friday 8am to 6pm.

Traffic management will remain in place for the duration of our works. Please note that the cable ducts will be installed in sections and the works will be completed in each area within a smaller timeframe than detailed above.

The three month period makes allowance to complete all works.

This work will not have any impact on your electricity supply.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]