Power cable duct installation work in west of Euston station
Work item: UK Power Networks - Modus works
Work Item Summary
- Project Phase
- Phase 1
- Location
- Cobourg Street, Euston Road, Hampstead Road, North Gower
- Contractor
- UK Power Networks
- Type of works
- Utility works / surveys
- Estimated Start Date
- 26/09/2022
- Estimated End Date
- 09/12/2022
What we are doing
UK Power Networks are in process of installing a new connection to the electricity network in the Camden area.
The works are progressing through the next sections and will affect areas in Drummond Street, Euston Street, North Gower Street, Cobourg Street and Starcross Street.
Works are due to commence on Monday 26th September and be completed early December 2022.
Working hours: Monday to Friday 8am to 6pm.
Traffic management will remain in place for the duration of our works. Please note that the cable ducts will be installed in sections and the works will be completed in each area within a smaller timeframe than detailed above.
The three month period makes allowance to complete all works.
This work will not have any impact on your electricity supply.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]