Update: power connection works on West Gate, Hanger Lane being paused, to restart in early October
Work item: HS2-SCS-25-1103
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Westgate
- Contractor
- SCS JV
- Type of works
- Power connection, Utility works / surveys
- Estimated Start Date
- 21/07/2025
- Estimated End Date
- 17/10/2025
What we are doing
We had been working to install a high-voltage (HV) connection to power the Westgate Ventilation Shaft and Headhouse site from 21 July to 7 September 2025.
We will be digging a small trench and joint bay for installing ducts below ground to pull through and connect the HV cable.
We will close a part of the footpath and cycle lane on West Gate near the Manhattan Apartments during this work. A pedestrian diversion will be in place. Cyclists will need to dismount from their bikes and use the pedestrian diversion route.
We will be using hand-held tools and a vacuum excavator. We will put up noise reducing barriers where possible to minimise disruption.
For further details and location map please follow the update notification below.