Proof House Business Park temporary access arrangements

Work item: HS2-EW-Align-Ph1-Bir-Cur-St-N4-Prog-works-49-15/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Curzon Street
Worksite Name
Curzon Station
Contractor
LM JV
Type of works
Enabling works
Estimated Start Date
19/07/2021
Estimated End Date
04/09/2021

What we are doing

Access to Proof House Business will be via the secondary access on New Canal Street. Traffic should access this via Curzon Street and New Canal Street . Traffic and pedestrian management measures will be in place as we carry out the ongoing works. Core working hours are 8am to 6pm, although staff may be on site up to an hour before and an hour after those times.