Public Right of Way W130b closure
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-5-09/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Cubbington
- Contractor
- BBV JV
- Type of works
- PRoW Closure
- Estimated Start Date
- 07/11/2022
- Estimated End Date
- 18/11/2022
What we are doing
We will be doing temporary utility diversions to enable the preparation for the construction of the over bridge. The closure is to facilitate the safe digging of trenches to installing ducting and reinstatement.
There will be a full closure with no public access during working hours – 8am-6pm, the Public Right of Way crossing will be open to the public outside of our working hours. The site team will place a foot plate over the excavation so pedestrians can cross the road.
This closure will allow us to keep users of the footpaths safe as we construct the line of route for HS2 at this location.