Reinstatement Works – Euston West

Work item: HS2-MW-CSJV-Ph1-Ca-S1-Prog-works-17-10/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden
Contractor
CS JV
Type of works
Road repairs
Estimated Start Date
18/10/2021
Estimated End Date
20/10/2021

What we are doing

Reinstatement Works West of Euston Station

North Gower Street Junction with Drummond Street
Reinstatement – 18 October 2021

On Monday 18th October CSJV will be carrying out reinstatement works to replace the current road surface. The works will take place in North Gower Street close to the junction of Drummond Street for a period of 1 day.

Euston Street junction with Cobourg Street – 18 October 2021

On Monday 18th October CSJV will be carrying out reinstatement works to replace the current road surface, the works will take place in Euston Street close to the junction of Cobourg Street.

Drummond Street junction with Cobourg Street – Monday 18 October

On Wednesday 18th October CSJV will be carrying out reinstatement works to replace the current road surface. The works will take place in Drummond Street close to the junction with Cobourg Street.

Euston Street – Monday 18th October

From Monday 18th October CSjv will be carrying out the installation of safety chains within the manhole on Euston Street, this work is expected to last for 2 days.

Gower Street Slip Lane – Tuesday 19th October

From Tuesday 19th October CSjv will be carrying out Anti-Skid resurfacing works on the Gower Street Slip Lane with Euston Road.

Gordon Street – Monday 18th October

From Monday 18th October CSjv will be carrying out Anti-Skid resurfacing works on Gordon Street.