Work item: HS2-MW-CSJV-Ph1-Eu-St-S3-Traf-47-12/10/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Euston station
Contractor
CS JV
Type of works
Road closure, Road repairs
Estimated Start Date
18/12/2021
Estimated End Date
18/12/2021

What we are doing

From 8am Saturday 18 December until 1pm Saturday 18 December 2021, CSjv will be carrying out Anti-Skid resurfacing works in the junction of Varndell Street and Hampstead Road. Installation of the surface is expected to only take a few hours.

Varndell Street remains closed with a diversion route via Robert Street and Stanhope Street.