Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-16-01/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Enabling works
Estimated Start Date
15/04/2022
Estimated End Date
30/09/2022

What we are doing

Removal of concrete slabs

Enabling works need to be carried out within the future footprint of the HS2 Euston station. These activities are
all within the site boundary and are anticipated to commence from late-April to autumn 2022.

The first of these activities include demolition of the former Ibis Hotel basement slab – see map below for site area. This will be carried out from late-April 2022 and will involve the use of a 20t excavator, 35t excavator with breaker and a vacuum excavator, where required.

We appreciate works can be noisy, and we have therefore included noise and vibration control measures to limit its impact. This includes high perimeter hoarding and where practicable, Heras fence panels will be fitted with acoustically absorbent blankets and placed around high noise emission activities.

 