Rescheduled – Rendering works at Canterbury House

Work item: HS2-EW-CSJV-Ph1-Ar-So-S1-Prog-works-9-03/08/2021_02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Canterbury Road
Contractor
CS JV
Type of works
Rendering/Painting
Estimated Start Date
14/05/2021
Estimated End Date
26/06/2021

What we are doing

What are we doing?

We are continuing the preparatory works in your area. The works for the preparation and installation of render and decorative paint finish on the west elevation of Canterbury House has been rescheduled and will now be starting from mid-May for a duration of six weeks. Please be advised our programme of works is indicative as it requires dry weather and temperatures of  5 degrees or higher. We will provide you with an update at https://hs2inkilburnandnortholt.commonplace.is/

We will be carrying out these works using mobile elevating work platforms  to provide temporary access to required areas. We do not expect these to be noisy works, however we will use acoustic barriers to help minimise any noise.

Parking spaces at Canterbury House will not be affected and access to the car park will be maintained at all times. These works will be supervised to help ensure the safety of residents as well as site personnel moving through the area.