River Pinn realignment update

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-09/05/2024_02

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
River Pinn
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
16/10/2024
Estimated End Date
02/11/2024

What we are doing

We wrote to you in May to let you know the details of the River Pinn realignment works from 23 May to 16 October 2024. These works are ongoing, however, due to the exceptionally wet weather in September, we need additional time to complete them, which will now take place until 2 November 2024.

The scope of works includes:

  • installing a dam and over pumping system to create a dry working environment to realign a section of the river.
  • forming a new channel along the consented route for the river realignment. This will include all the necessary aquatic features, and measures to preserve existing wildlife in the river.

We are sorry for any disruption or inconvenience these works may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.

 