River Pinn Realignment with Footbridge and Footpath construction

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Wat-1-09/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
River Pinn
Worksite Name
Copthall
Contractor
SCS JV
Type of works
Footbridge construction, Footpath construction, River realignment
Estimated Start Date
23/05/2024
Estimated End Date
16/10/2024

What we are doing

From 23 May to 16 October 2024, we will be carrying out River Pinn realignment works. We’ll install a new footbridge which will reconnect the U45, U47 and U46 public rights of way and create a new footpath to replace the existing U47.
The scope of works includes:

The installation of a dam and over pumping system to create a dry working environment for the realignment of a section of the river Pinn.

The formation of a new channel along the consented route for the river realignment. This will include all the necessary aquatic features and measures are being taken to preserve existing wildlife in the river.

The construction of a new footpath along the realigned river course and installation of permanent drainage outlets.

The installation of the new footbridge structure over the new river channel to connect the U45, U46 and U47 Public Rights of Way.