Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Hampton in Arden, Solihull
- Estimated Start Date
- 27/03/2023
- Estimated End Date
- 26/05/2023
What we are doing
Road closure A45 East Way Loop
The new railway will pass under the A45 as it approaches the new interchange station. This requires significant work to the road and its adjoining slip road known as ‘East Way’. Before these works can take place, a number of utilities need to be moved and diverted to make sure that our works do not have an impact on the supply.
This work will be done in two phases.
Phase one will require the total closure all day and all night of the ‘loop’ section that joins the westbound carriageway of the A45 to the East Way. This will be closed from 27 March until 21 April
Phase two will require the closure of the loop section and the west bound slip road leading towards Stonebridge Island but this time we will only need to close the road at night from 9pm until 5am between 27 April until 26 May.
A fully signed diversion will be in place for both phases.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]