View route map
Road closure and traffic management, Rugby Road, Cubbington
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-43-13/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Cubbington
- Contractor
- BBV JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 04/09/2023
- Estimated End Date
- 22/09/2023
What we are doing
To complete the installation of temporary vehicle restrain system at Rugby Road, we will need to install two-way temporary traffic lights.
To complete the road improvement works and the white lines, Rugby Road will be closed.
Two-way temporary traffic lights in place, from 4 to 8 September 2023 from 8am to 6pm, please refer to map 1 on the notification.
A section of Rugby Road will be closed from 11 to 15 September 2023 and 18 to 22 September 2023 from 9.30am to 3.30pm, full diversion is in place, please refer to the maps.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]