Road closure, Bowood Lane
Work item: FUS_AWN_0232 HS2-EW-Fusion -Ph1-Ar-Ce-C2-Eco-43-23/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 19/07/2021
- Estimated End Date
- 13/08/2021
What we are doing
In preparation for the main construction works we are continuing with
our works along the HS2 route. This includes further works in the local
area during July and August 2021. In order to complete these works, we
will need to put in place a night time road closure on part of Bowood
Lane between 19 July – 13 August 2021. The road closure will be in
place between the hours of 8pm – 6am from the Bowood Lane T
junction up to Kings Lane. Kings Lane will remain open for through
traffic. Pedestrian access alongside Bowood Lane will be maintained
during the road closure. The lane will be open for vehicular use as usual
outside of these hours.