Road Closure – Frith Hill, South Heath

Work item: HS2-MW-Align-Ph1-Ar-Ce-C2-Traf-20-01/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
South Heath
Worksite Name
North Portal
Contractor
Align JV
Type of works
Road closure
Estimated Start Date
19/04/2022
Estimated End Date
02/05/2022

What we are doing

We need to move our site hoarding and utilise the layby at Weights and Measures. This will provide more space inside the site where we are constructing the barrettes. To do this safely, Frith Hill, South Heath will be closed to traffic in both directions from 9.30am on 19 April to 3.30pm on 2 May during weekdays only. The road will be fully open on weekends.