Road closure of Breakspear Road South for conveyor bridge removal
Work item: HS2-SCS-25-1320
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Road closure
- Estimated Start Date
- 03/10/2025
- Estimated End Date
- 05/10/2025
What we are doing
From 8pm on Friday 3 October to 8pm on Sunday 5 October 2025, we will remove the conveyor bridge over Breakspear Road South, located between the Chiltern Railway bridge and the HS2 Breakspear Road South bridge.
These works will be carried out 24/7 over a whole weekend which will require a full road closure on a section of Breakspear Road South.
We will dismantle the conveyor bridge in sections using an excavator before lifting them out with a crane and transporting the sections off site. These works will be carried out 24/7 over a whole weekend.
Please note, these works can only be carried out under rail possession, therefore, to ensure completion we have a contingency date in place from 8pm Friday 17 October to 8pm Sunday 19 October.