Road closure on Frith Hill, South Heath Leg, Great Missenden
Work item: HS2-MW-Align-Ph1-Ar-No-N2-CR-19-28/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Worksite Name
- Frith Hill
- Contractor
- Align JV
- Type of works
- Road closure
- Estimated Start Date
- 13/03/2023
- Estimated End Date
- 16/04/2023
What we are doing
The railway line also requires an electrical supply. To do this, UK Power Networks (UKPN) will excavate the highway on Frith Hill to install new underground cables, connecting the North Portal to their network. Frith Hill, South Heath Leg, will be closed to traffic from:
13 March to 16 April. This will be a 24/7 continuous closure that will remain in place throughout the duration of the works.