Road closure on Park Village East north – 27 June
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-08/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Park Village East
- Contractor
- SCS JV
- Type of works
- Hoarding works, Road closure
- Estimated Start Date
- 27/06/2022
- Estimated End Date
- 27/06/2022
What we are doing
Temporary road closure for maintenance to lay-by – 27 June
On Monday 27 June, we will temporarily close the road at the northern end of Park Village East while amend the hoarding for the lay-by and install safety and security signage. We will install the traffic management at 8am and remove it once the works are finished. We expect these works to take about half a day to complete.
Vehicles will not be able to access Park Village East via Parkway junction while the road is closed and will instead be diverted via Albany Street, Robert Street and Stanhope Street or via Arlington Road, Delancey Street, Albert Street and Mornington Street.
We will maintain access for businesses and residents to the northern end of Park Village East via Mornington Street bridge and Park Village East south. A traffic marshal will be onsite during working hours to assist resident vehicles passing the worksite.
Vehicles may be delayed for a few minutes while we clear the road to allow them to pass. We apologise for any inconvenience this may cause.
We will continue to carry out works to the lay-by, as we begin to test and operate it.
Please see the notification below.
Download information relating to these works
Find out more about