Stanhope Street street to be opened from the evening on 15 September
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Traf-1-21/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Park Village East, Stanhope Street
- Contractor
- SCS JV
- Type of works
- Road closure, Utility works / surveys
- Estimated Start Date
- 07/08/2023
- Estimated End Date
- 15/09/2023
What we are doing
Utility works on Stanhope Street
We are installing a new cable route from Lidlington Place to Varndell Street via Granby Terrace, to replace the existing route next to Hampstead Road.
Update: Stanhope Street will be open from the evening on 15 September
On 7 August we closed the road and suspended parking bays on the corner of Stanhope Street and Park Village East for the next phase of work. We now completed this work earlier then planed. We will remove the traffic management in the evening on 15 September and open the road.
We will keep you updated on further phases of utility works in the Regents Park Estate in due course.