Road closure on Varndell Street – 14 October 2024 to 28 May 2025

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-26/09/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Hampstead Road, Varndell Street
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
14/10/2024
Estimated End Date
15/10/2024

What we are doing

Hampstead Road temporary utilities diversion

We are currently carrying out utility diversion works on Hampstead Road.

We need to temporarily divert existing utilities on Hampstead Road before we extend Hampstead Road bridge. From April 2024 to April 2025, we will remove all the utilities from Hampstead Road and redirect them across Granby Terrace bridge and over the retaining wall within our worksite. After we extend Hampstead Road bridge, we will permanently reinstall the utilities on Hampstead Road.

From 14 October 2024 to 28 May 2025 we will work in the southern section, which will require road closure on Varndell Street.  

Please see below the latest updated programme of phased works on Hampstead Road between Granby Terrace bridge and Varndell Street.

SectionTraffic impactsStartFinish
Northern SectionNorthbound cycle lane closure (current traffic management set up)7 Aug 202410 Nov 2024
Southern SectionRoad closure on Varndell Street14 Oct 202428 May 2025
Northern SectionNorthbound and southbound outer lane closure on Hampstead Road15 Nov 202414 Apr 2025
Southern SectionLane closure on Varndell Street and southbound lane closure on Hampstead Road28 May 202528 Oct 2025
Northern SectionSouthbound footpath and cycle lane closure15 Apr 20258 May 2025
Northern SectionNorthbound footpath and cycle lane closure11 Mar 202522 Apr 2025

We will update you with further detail of the works in these phases nearer the time.

We apologise for any inconvenience these works may cause.

For further details and location maps please follow the link to the update notification below.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]